- 2019 ELIMAIA launches trial run in experimental hall
- 2018 Start of trial operation
Experimental Hall 1 (Material and Biomolecular Applications) Using L1 Laser
- 2016-2017 Phase II
Laser & amp; experimental installation
Completion of construction works
- 2011 April The European Commission approved the financing of the ELI Beamlines project
- 2011 August Project budget (278 million Euro) signed by the Minister of Education, Youth and Sports
- 2011 December Technical Design Report Completed
- 2012 July Finalization of construction documentation
- 2012 September Launch of excavation work
- 2013 May Building construction started
- 2015 December Phase I completed